1. Plant Cost Coefficients & Capacity Limits (Cost Equation: Fi = aiPi² + biPi + ci [INR/hr])
2. Total Demand & Power Allocation Controls
MW
Adjust power sliders manually to observe how arbitrary power sharing increases cost compared to optimal ELD:
Total Generation Matches Demand
3. Economic Dispatch Results
TOTAL GENERATION COST
₹ 0.00 / hr
Plant 1 Cost (F1)
₹ 0.00 / hr
IC1: 0.0 INR/MW-hr
Plant 2 Cost (F2)
₹ 0.00 / hr
IC2: 0.0 INR/MW-hr
Plant 3 Cost (F3)
₹ 0.00 / hr
IC3: 0.0 INR/MW-hr
Incremental Cost (IC = dF/dP): At optimal dispatch, Incremental Costs for all non-bounded generators become equal ($\lambda$).